A team from Naval Energies met IFREMER’s staff in La Martinique from July 27th to 30th in order to prepare the test bench modifications after the summer (integration of a new refrigeration unit and new heat exchangers, calibration of sensors, automatization of ozonation equipment, oxidants mesurements and biopolymers injection…)
Further to the equipment shipment to La Martinique in september, the modifications will be implemented with commissionning of the test bench by the end of october
*Deadlines will be updated where necessary due to current COVID-19 restrictions
NOV 2019
Official start of project
FEB 2020
Kick-off meeting.
OCT 2020
Finalisation of test bench conditions.
NOV 2020
Begin testing phase for a duration of 21 months.
JULY 2021
Delivery of interim report.
JULY 2022
Delivery of report detailing test bench results.
OCT 2022
Final presentation of SIMBIOSE project.